Iowa DOT e‑ticketing requirements

Required on some projectsIowa Department of Transportation (Iowa DOT)

Last verified September 26, 2026

Iowa DOT's Developmental Specification DS-23032, effective October 17, 2023, requires electronic tickets for all loads of the primary material on projects where it is included: asphalt (flexible paving mixture) on HMA resurfacing projects or ready-mixed PCC on PCC paving projects. Ticket data goes to Iowa DOT's portal by API before the truck leaves the plant. E-tickets for other materials are optional.

Required on some projects: E-tickets are required only on contracts that include the provision or meet a size threshold.

Key dates

October 17, 2023
DS-23032 Developmental Specifications for Electronic Ticketing effective (replaces earlier DS-15095)
February 18, 2025
Example: DS-23032 included in a PCC paving contract let February 18, 2025 (Contract 31-0039-025)

Materials and project scope

  • Asphalt (flexible paving mixture)
  • Ready-mixed portland cement concrete

Contracts that include DS-23032; required only for the primary material (HMA on an HMA resurfacing project, PCC on a PCC paving project). Other materials at the contractor's option. Which share of lettings include DS-23032 was not determined.

Spec references

  • DS-23032: Developmental Specifications for Electronic Ticketing

Data requirements

HTTPS POST of JSON documents to https://iowa.dot-portal.io with a customer-specific API key in the HTTP header. Transmit before the truck leaves the plant; transmit updates within 5 minutes of a change. Test data sharing at least 30 days before project start. Net weight (or volume for concrete) to 0.01 ton or CY and running daily total. All tickets: date, Iowa DOT project number, contractor, supplier, unique truck ID, plant/scale, loaded time, other status times as available. PCC: water/cement time, batch weights, water data, admixtures, cementitious weights, CPI name and certificate number. HMA: material type, gross and tare if not automatic, net weight, mix design number. Payment is incidental to the material.

What contractors should do

  1. Look for DS-23032 in the proposal; if present, e-tickets are required for the project's primary material.
  2. Have your supplier connect its plant ticketing system to Iowa DOT's portal by API; any plant ticketing system is allowed.
  3. Test the data connection at least 30 days before project start and raise it at the preconstruction meeting.
  4. Price e-ticketing into the material; there is no separate pay item.

What haulers should do

  1. Make sure your truck ID matches what the supplier uses on the ticket; unique truck ID is required.
  2. Do not leave the plant before the ticket is created; DS-23032 requires transmission before the truck leaves.